Historical delay descriptions from the frozen NYC Open Data Capital Projects Delays extract. These labels power historical training and give a menu of the shapes of delay that have occurred on similar projects. They are not real-time.
Null `delay_desc` in the legacy row means no labeled reason, not proof of no delay.
Scope: DDC-managed projects only in v1. The public source labels other managing agencies too, but this build ingests DDC-only rows. See the methodology » Limits for the citywide roadmap. Observed labels: DDC 7.
Scope: DDC-managed projects. 12,737 historical rows; 2,496 of them are unlabeled (empty delay reason). Bars show the labeled subset only.
| Reason | Agency | Borough | Category | Original budget | Overrun % | Published |
|---|---|---|---|---|---|---|
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | REHABILITATION OF CITY-OWNED OFFICE SPACE | $3,740 | 160% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | QUEENS | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $276 | 3109% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | AUGMENTATION OF WATER SUPPLY SYSTEMS | $389 | 442% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BRONX | BUILDING SYSTEMS AND INFRASTRUCTURE | $35,249 | 8% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $1,436 | 74% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | QUEENS | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $1,056 | 335% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $17,750 | 163% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | REPLACEMENT OR AUGMENTATION OF EXISTING SYSTEMS | $2,308 | 7% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $17,175 | 91% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BRONX | BUILDING SYSTEMS AND INFRASTRUCTURE | $51,374 | 87% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | CHILD WELFARE FACILITIES | $15,205 | 329% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | OCME | $458 | 1288% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $569 | 472% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $1,056 | 208% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $6,540 | 116% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | AUGMENTATION OF WATER SUPPLY SYSTEMS | $244 | 5735% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | CITYWIDE | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $563 | 280% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | AUGMENTATION OF WATER SUPPLY SYSTEMS | $71,769 | -4% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $25,804 | 121% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | CITYWIDE | SUPPORT SPACE | $100,600 | 124% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BRONX | BUILDING SYSTEMS AND INFRASTRUCTURE | $4,400 | 241% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BRONX | BUILDING SYSTEMS AND INFRASTRUCTURE | $19,189 | 23% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $3,700 | 362% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | REHABILITATION OF CITY-OWNED OFFICE SPACE | $17,078 | 0% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $5,776 | 175% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN EXTENSION | $7,244 | 714% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $18,872 | 383% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $3,769 | 29% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $7,126 | 55% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $1,594 | 309% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | ESSENTIAL RECONSTRUCTION OF FACILITIES | $10,045 | 74% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $11,730 | 228% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | AUGMENTATION OF WATER SUPPLY SYSTEMS | $14,039 | 0% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $14,445 | 144% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | DEPARTMENT FOR THE AGING BUILDING RECONSTRUCTION | $1,000 | 2043% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | QUEENS | GREEN INFRASTRUCTURE PROGRAM | $5,082 | 243% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $9,413 | 487% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | AUGMENTATION OF WATER SUPPLY SYSTEMS | $6,878 | 27% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | New Jail Facilities | $2,188,413 | -6% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | New Jail Facilities | $2,021,426 | 65% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | BRONX | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $6,305 | 37% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | QUEENS | New Jail Facilities | $97,683 | -2% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $4,600 | -36% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BRONX | BUILDING SYSTEMS AND INFRASTRUCTURE | $16,930 | 66% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO CHANGES IN SCOPE/DESIGN | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | TRUNK AND DISTRIBUTION MAIN REPLACEMENT | $1,920 | 839% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | QUEENS | New Jail Facilities | $2,113,874 | -6% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | RENOVATION OF OTHER CITY-OWNED FACILITIES | $80,000 | 113% | Oct 26, 2023 |
| null (unlabeled) | DEPT OF DESIGN & CONSTRUCTION | MANHATTAN | SHELTERS FOR HOMELESS INDIVIDUALS | $1,300 | 21% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO UNFORESEEN SITE/FIELD CONDITION | DEPT OF DESIGN & CONSTRUCTION | BRONX | New Jail Facilities | $2,073,288 | -7% | Oct 26, 2023 |
| PROJECT DELAYED DUE TO BUDGETARY CONSTRAINTS | DEPT OF DESIGN & CONSTRUCTION | BROOKLYN | RECONSTRUCTION/RENOVATION OF COURT FACILITIES | $3,269 | 874% | Oct 26, 2023 |