NYC Prototypes
Skip to main content
BBL 2023430032 · BIN 2001019 · Bronx · Block 02343, Lot 0032

500 GRAND CONCOURSE

Article 320Pathway source: CBL PDF row · CP0_article_320_2024CBL revision date 2026-06-16Open CBL source PDF
Buildings on lot 1
← Buildings

Article 320 · numerical caps & computed exposure

How this is computed
PeriodOccupancyGFACapActualDeltaEst. penaltyStatusMethodology
2024-29B(medium)135,370 sqft1,145.2 tCO2e1,515.7 tCO2e+370.4$99,275
Over capEJ · PEJA fallback
v1.0
2030-34B(medium)135,370 sqft613.2 tCO2e1,515.7 tCO2e+902.4$241,852
Over capEJ · PEJA fallback
v1.0

Cap = Σ (occupancy_coefficient × gross_floor_area) using DOB LL97 rules; actual GHG is the most recent LL84 filing. Delta is positive when actual exceeds cap. Estimated penalty is DOB's public $268/tCO2e × delta with a 30-day grace applied via penalty_estimate_usd.

LL84 GHG emissions history

Actual tCO2e reported to LL84 by report year. Each bar links to the raw LL84 row identifier under the chart for auditability.

2023903.6 tCO2e20241,515.7 tCO2e
YearProperty typeGHGProperty GFASite EUISource EUIES scoreSource
2023College/University903.6 tCO2e135,370 sqft124.2132.9-5zyy-y8am / 33910493
2024College/University1,515.7 tCO2e135,370 sqft165.0241.9-5zyy-y8am / 33910493

Enforcement events (all DOB + ECB + OATH data cross-linked to this BBL)

Open on enforcement page →
0 LL97-specific events · 17 building-scoped context events.
DOB violation filed0 LL97 · 6 scoped
ECB summons issued0 LL97 · 3 scoped
Safety context record0 LL97 · 8 scoped
StageEvent dateViolationSeverityStatusPenaltySource
Safety context recordbuilding-scoped2026-03-17
FTC-AEU-HAZ
-Active-855j-jady
DOB violation filedbuilding-scoped2026-03-02
C-CONSTRUCTION OTHER OPTIONAL
DEPARTMENT OBSERVED FAILED FAÇADE AT SOUTHERN EXPOSURE. 300 SQ FT COLLAPSED BETWEEN 4TH/5TH FLOORS. NETTING/MASONRY HAZARD. REMEDY: PREPARE STABILIZATION/REPAIR PLAN FOR SOUTH FAÇADE.EMAIL SIGNED/SEALED PLANS TO CSE BY 3/10/26. PULL PERMIT BY 4/15/26
-V-DOB VIOLATION - ACTIVE-3h2n-5cm9
DOB violation filedbuilding-scoped2026-03-02
C-CONSTRUCTION OTHER OPTIONAL
DEPARTMENT OBSERVED FAILED FAÇADE AT SOUTHERN EXPOSURE. 300 SQ FT COLL COLLAPSED BETWEEN 4TH/5TH FLOORS. NETTING/MASONRY HAZARD. REMEDY: RETAIN NYS RDP FOR MONITORING PLAN PER BC 1705.25.8.1. EVALUATE NETTING. SUBMIT TO DOB BY 3/10/26. PROVIDE WEEKLY DATA
-V-DOB VIOLATION - ACTIVE-3h2n-5cm9
Safety context recordbuilding-scoped2026-01-08
FTF-PL-PER
Cycle 2, Sub-cycle A (premises is in Community District 1)
-Active-855j-jady
DOB violation filedbuilding-scoped2025-11-14
LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
-V-DOB VIOLATION - ACTIVE-3h2n-5cm9
Safety context recordbuilding-scoped2025-11-14
LBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
-Active-855j-jady
ECB summons issuedbuilding-scoped2025-11-08
Construction
28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
ECB #35717686J
CLASS - 1ACTIVE$2,5006bgk-3dad
DOB violation filedbuilding-scoped2025-11-08
C-CONSTRUCTION OTHER OPTIONAL
EWO OBSERVED A 5 STORY MASONRY CAVITY WAL FACADE WHERE APPROX 300SQ FT OF BRICKS HAD FAILED AND COLLAPSED ON 11/6/25. REMEDY: IMMEDLY RETAIN A NYS RDP TO INSPECT/SUPERV THE INSTALLATION OF SAFTY MEAS @ ALL EXP SUBMIT S/S REPORT BY RDP INDIACTING WHAT MASONRY REPAIR AND/OR STABLIZ WORK IS REQUIRED. AND THE MEANS/METHOD ON HOW THE WORK WILL BE DONE
-V-DOB VIOLATION - ACTIVE-3h2n-5cm9
DOB violation filedbuilding-scoped2025-11-08
C-CONSTRUCTION OTHER OPTIONAL
FTM.OBSERVED A 5 STORY MASONRY CAVITY WALL FACADE WHERE APRROX 300SQFT OF BRICKS HAD FAILED/COLLASPSED ON 11/6/25.REMEDY: IMMEDLY RETAINA NY RDP TO INSPECT 100%HANDS ON WITH PROBE THE ENTIRE FACADE OF THE BLDG RDP TO ASSESS & RECOMMED REPAIRS. SUBMIT REPORTS BY 11/14/25 AT FACADE@BUILDINGS.NYC.GOV. INSTALL ALL SAFETY MEASURES
-V-DOB VIOLATION - ACTIVE-3h2n-5cm9
ECB summons issuedbuilding-scoped2025-11-08
Construction
28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
ECB #35717685H
CLASS - 1ACTIVE$2,5006bgk-3dad
ECB summons issuedbuilding-scoped2025-11-08
Construction
28-301.1 FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER
ECB #35717684X
CLASS - 1ACTIVE$2,5006bgk-3dad
Safety context recordbuilding-scoped2025-04-23
-
-Active-855j-jady
Safety context recordbuilding-scoped2024-10-11
FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
-Active-855j-jady
Safety context recordbuilding-scoped2024-10-11
FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
-Active-855j-jady
Safety context recordbuilding-scoped2024-10-11
FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
-Active-855j-jady
DOB violation filedbuilding-scoped2024-09-23
LBLVIO-LOW PRESSURE BOILER BOILER REQUIRED
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION
-V-DOB VIOLATION - ACTIVE-3h2n-5cm9
Safety context recordbuilding-scoped2024-09-23
LBLVIO
Violation Issued-Failure To File 2023 External Low Pressure Inspection Report
-Active-855j-jady

Records are the union of DOB Violations (3h2n-5cm9), ECB (6bgk-3dad), Safety Violations (855j-jady), OATH Hearings (jz4z-kudi), and OATH Trials (y3hw-z6bm) that we could link back to this BBL via BIN or address parsing. Events not tagged LL97-specific are shown as building-scoped context. See methodology · enforcement linking.

Fields we cannot show here (internal DOB data not yet public)

Processing lifecycle

DOB's internal BEAM system tracks per-building compliance stages, RCE / decarbonization plans, and mitigation credits. Those fields are not yet published as an open dataset. When DOB releases them, this product will show them here without a schema migration. Until then, the following are known gaps for this building:

  • Assessed penalty (vs theoretical)
    Actual penalty DOB assessed against a building, distinct from the theoretical over-cap exposure computed from LL84 emissions.
    Simulated · internal DOB data not yet public
    Best-effort shadow field: ecb_summons_issued
    Public release status: announced_not_yet_released
  • Audit assignment
    Buildings selected by DOB for LL97 filing audit and the audit stage.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Audit outcome
    Result of an LL97 audit (accepted / correction ordered / penalty referred).
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Extension flag
    Whether a per-building filing was accepted under a filing extension (June 30 grace or BEAM extension to August 29).
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Filing received date
    Timestamp DOB received a per-building LL97 compliance filing.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Good-faith effort application
    Whether an owner has applied for a good-faith effort determination and its status.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Mediated resolution application
    Application for the LL97 mediated resolution process and its outcome.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Notice of deficiency status
    Whether a notice of deficiency has been issued for a building and its current stage.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Per-building filing status
    Filing status for each covered BBL/BIN combination (filed / late / non-filed / exempt) as tracked in DOB's BEAM system.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • Pre-OATH correspondence
    DOB correspondence with owners before an OATH matter is opened (notice of deficiency, cure letters).
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • RDP attestation
    Registered Design Professional attestation attached to each per-building compliance filing.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • RECs / offsets claimed
    Renewable Energy Credits and beneficial-use offsets claimed to reduce reported emissions.
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
  • 60-day cure window
    The 60-day cure window state for a building under LL97 enforcement (open / cured / expired).
    Simulated · internal DOB data not yet public
    Public release status: announced_not_yet_released
Every number on this page traces back to a Socrata dataset row or a CBL PDF revision. Where DOB does not publish a computable field (pathway, internal BEAM stage, compliance decision), we say so on the record instead of hiding the gap. See methodology.